By Jay ЁЯУНA major power project that had remained stalled for nearly a decade in Pathadi village of Korba district, Chhattisgarh, has finally been revived. Adani Power has successfully commissioned the first 660 MW unit of the 1,320 MW Korba power expansion project. Behind this milestone are nearly two years of relentless effort by a team of more than 250 engineers, Indian equipment manufacturers, partners, and thousands of workersтАФwith roughly 10,000 people working on site during peak construction.
Advt

From Acquisition to Revival: Tough Challenges and Strong Resolve
The new chapter for the project began in August 2024, when Adani Power acquired Lanco Amarkantak Power Limited for тВ╣4,101 crore through the NCLT process. At the time, a 600 MW plant was operational, while the 1,320 MW expansion project lay incomplete:
-
Years of Stalled Work: Roughly 70 percent of the expansion work had been completed, but construction had been halted since 2016. Because work remained suspended for nearly ten years, the condition of machinery, structures, and supporting systems had to be reassessed from scratch.
-
Missing Records and Original Contractors: Several crucial documents and drawings from the earlier project were either unavailable or insufficient, and the original engineering and construction contractors were no longer associated with the project.
-
A Different Engineering Challenge: The task was distinct from building a greenfield power plant. Engineers had to examine a decade-old incomplete facility, inspect its equipment and structures, and decide which components could be reused and which needed replacement or reinforcement.
-
System Inspections and Grid Connectivity: The team thoroughly inspected key systems including the boiler, turbine-generator, electrical equipment, coal handling setup, and water systems. Where historical records were missing, engineers recreated necessary engineering documents and designs based on actual site conditions, alongside putting in place the required transmission infrastructure to deliver power to the grid.
With the first 660 MW unit now operational, the team is working to commission the second 660 MW unit over the coming months. Once completed, the total installed generation capacity of the Korba station will reach 1,920 MW.
Community Development Across Nearby Villages
Alongside reviving the power facility, the Adani Foundation has rolled out initiatives focused on education, healthcare, and community infrastructure in surrounding villages:
| Sector | Key Initiatives and Milestones |
|---|---|
| Education and School Infrastructure |
тАв Distributed 4,200 school kits across 50 government schools in 24 villages
тАв Provided 220 dual desks across 9 schools
тАв Installed RO water filters in 15 schools, benefiting over 1,800 students and staff
тАв Built toilets in 3 schools, aiding more than 800 students
тАв Upgraded facilities at 18 anganwadi centers across 11 villages
тАв Establishing a Science and Convention Center in Korba |
| Project Udaan | тАв Conducted 164 visits since October 2025, enabling 8,281 students to tour the Korba power plant and learn how electricity is generated |
| Healthcare Services | |
|
тАв Operating mobile health services across 18 villages since June 2025, reaching around 17,000 people
тАв Organized 6 multi-specialty health camps along with services such as eye check-ups
тАв Distributed 65 assistive devices to support mobility and daily living |
|
| Rural Lighting |
тАв Installed 240 solar street lights across 15 villages in 11 gram panchayats, benefiting more than 25,000 residents
тАв Set up 5 solar high-mast lights in market and haat areas |
Ultimately, the revival in Korba reflects more than restarting dormant machineryтАФit highlights how engineering, teamwork, and community outreach can bring a stalled project back to life.